Overview

This help article will cover STACK’s Quick Assemblies for Division 6. We currently offer assemblies for FRP and Sheathing.


More on Quick Start Assemblies


Table of contents

06 Wood, Plastics & Composites

FRP

FRP - Linear

Summary: This assembly is designed for a Linear takeoff

Variables:

  • Wall Panel Height In Feet – this will be used to calculate labor and adhesive.

Required Items:

These items will be automatically added to your takeoff.

  • FRP End Caps – they are figured for both the top and bottom of all panels in 10’ pieces, based on the linear footage from your takeoff.

  • FRP Labor – by the square foot.

  • FRP Adhesive – 3.5 gallon buckets, based on the linear footage of the takeoff and panel height variable.

  • FRP Divider Bar – taotal count of pieces based on the linear footage of your takeoff spaced 4 feet apart.

Item Groups:

These groups contain a selection of items to choose if needed.

  • Choose Panel Size – a selection of panels that are 4’ wide and 8’, 9’, 10’ or 12’ high.

FRP Corners

Summary:

This assembly is designed for a Count takeoff

Variables:

There are no variables in this assembly.

Required Items:

There are no required items in this assembly.

Item Groups:

These groups contain a selection of items to choose if needed.

  • Choose Corner Piece – either an inside or outside corner piece that reflects the count total from your takeoff.

Sheathing

Sheathing – Area & Surface Area

Summary:

This assembly is designed for either an Area or Surface Area takeoff

Variables:

There are no variables in this assembly.

Required Items:

These items will be automatically added to your takeoff.

  • Sheathing Labor – in square feet, taken from the takeoff measurement.

Item Groups:

These groups contain a selection of items to choose if needed.

  • Choose Sheathing Material – 4x8 sheets of OSB, Plywood or DensGlass

Sheathing – Linear

Summary:

This assembly is designed for a Count takeoff

Variables:

  • Sheathing Height In Feet – needed to calculate all items in this assembly.

Required Items:

  • Sheathing Labor – in square feet, taken from the takeoff measurement and sheathing height variable.

Item Groups:

These groups contain a selection of items to choose if needed.

  • Choose Sheathing Material – 4x8 sheets of OSB, Plywood or DensGlass, based on the takeoff measurement and sheathing height variable.