Table of contents
Overview
This help article will help the reader in the use of the STACK concrete catalog, whether a veteran in the trade or a new employee with no construction experience. The STACK concrete catalog contains assemblies for all sorts of flatwork and foundation structures. Flatwork assemblies do not contain rebar items, so adding an additional rebar assembly may be necessary. Rebar-only assemblies are available that mimic a concrete counterpart. Not only are they good for rebar-only contractors, but also can be added for more complicated rebar configurations.
Terminology
We recognize that different regions use different terms for their trades. This list should help you better understand the choices STACK assemblies offer.
Footer, Beam, Stem Wall – As far as STACK assemblies are concerned, these terms are interchangeable. All refer to structures in the foundation with length, width, and depth measured using a Volume 3D or Linear takeoff.
Column, Pier – these terms refer to concrete that typically has a larger vertical component, whether into the ground or supporting part of the structure above.
Continuous Rebar – This is rebar that runs along the length of the footer or beam
Cages, Stirrups – These terms refer to rebar bent into a circle or rectangle or U-shape surrounding and supporting vertical or continuous rebar.
Horizontal Rebar - this refers to two different types of rebar, depending on the assembly. In the “Concrete Wall – 3D” assembly it refers to rebar that runs along the length of the wall and spaced evenly going up the wall. In footer and beam assemblies, horizontal rebar sits perpendicular to the continuous rebar with length approximately equal to the width of the footing or beam. This type of rebar is sometimes called transverse rebar or cross-bridging.
Bar Lap Count – the number of rebar diameters needed to make up the splice length. This is often confused with the splice length itself. The equation to determine this number is Rebar Diameter X Bar Lap Count = Splice Length. For example, if we have #4 rebar and a 2 foot splice length, our equation is .5 X Bar Lap Count = 24 then Bar Lap Count = 24/.5 = 48.
Assemblies
03 30 00 – Rebar
Corner Rebar
Summary: This assembly is designed for a Count takeoff and can be used for corners, T intersections and X intersections. Currently, rebar is only available by the linear foot in this assembly.
Variables:
Number Of Rebar Needed - Enter the number of pieces of rebar needed for each count
Length Of Rebar Need In Feet - Enter the length of each piece of rebar
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Rebar for "L Intersection" Corner - Uses both variables and takeoff total for calculations
Rebar for "T Intersections" - Uses both variables and takeoff total for calculations and multiples the result by 2
Rebar for "+ Intersections" - Uses both variables and takeoff total for calculations and multiples the result by 4
Rebar For Beam - Linear
Summary: This assembly is based on a Linear takeoff and yields continuous rebar, rebar stirrups, tie wire and labor
Variables:
Stirrup Spacing In - used to calculate stirrup rebar
Beam Width In - width of the concrete, used to calculate stirrup rebar
Continuous Rebar Count - how many pieces or rebar run along the length of the beam
Rebar Waste 1 to 100 - enter a number as a percentage of waste you want added
Rebar Stock Length Feet - the length of the rebar you typically order
Bar Lap Count - Click here for a description
Crew Production Lbs Per Hour - used to calculate labor hours
Cont Bar Size - the number of rebar you chose from the item group (3, 4, 5, etc.), used for calculating tie wire
Stirrup Bar Size - the number of rebar you chose from the item group (3, 4, 5, etc.), used for calculating tie wire
Beam Depth In - depth of the concrete, used to calculate stirrup rebar
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire - by the roll, calculated using all variables
Item Groups:
These groups contain a selection of items that must be chosen if required
Continuous Rebar - rebar by the pound or linear foot
Rebar Stirrups - rebar by the pound or linear foot
Reinforcing Crew For Cont. Bars - yielding crew hours
Rebar For Column, Round - Count
Summary: This assembly is designed for rebar for round columns, both vertical and cages. You could also use this for round piers that require the same rebar configuration. It is designed for a count takeoff.
Variables:
Column Diameter In – Enter the diameter of the column in inches.
Column Height In – Enter the height (vertical dimension) of the column in inches, can also be the depth if this is a pier.
Vertical Rebar Count – Enter the number of pieces of rebar that run vertically in the column.
Rebar Waste 1 to 100 – Enter a percentage waste factor for rebar.
Cage Rebar Spacing In – Enter the spacing of cages in inches.
Anchors Per Column – The number of anchor bolts required per column.
Vert Bar Size – Used to calculate tie wire and rebar labor crew, enter the vertical rebar’s number (3, 4, 5, etc.).
Cage Bar Size - Used to calculate tie wire and rebar labor crew, enter the cage rebar’s number (3, 4, 5, etc.).
Crew Production Lbs Per Hr – For your rebar placement crew, enter the amount of rebar they can place in pounds.
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire – based on the number(s) of your rebar chosen in variables and the column dimensions.
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Vertical Rebar – Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the rebar count
Choose Cage Rebar - Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the cage spacing
Choose Anchor Bolts – Items calculated based on takeoff total and bolts per column variable
Rebar Crew In Pounds Per Hour – Choose a rebar crew, total hours calculated based on all rebar variables and takeoff total
Rebar For Column, Square - Count (2021)
Summary: This assembly is designed for rebar in rectangular concrete columns as vertical and cage rebar.
Variables:
Column Height In – the column’s vertical dimension, whether height or depth, entered in inches
Vertical Rebar Count – how many pieces of rebar are placed vertically in the column
Rebar Waste 1 To 100 – enter a percentage waste factor for rebar
Cage Rebar Spacing In – enter the spacing of your cages as they go up the column in inches
Column Width In – one of the horizontal dimensions of the column
Column Length In – the other horizontal dimension of the column
Vert Bar Size - enter the vertical rebar's number, used for calculating tie wire
Cage Bar Size - enter the cage rebar's number, used for calculating tie wire
Anchors Per Column - how many anchor bolts you need per column
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire – based on the number(s) of your rebar chosen in variables and the column dimensions
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete – Items for structural concrete from 2500 to 5500 PSI, calculated based on takeoff total and column dimension variables
Form Material – Contains sonotube items from 8” to 48” diameter
Vertical Rebar – Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the rebar count
Cage Rebar - Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the cage spacing
Formwork Crew In Columns Per Hour – Choose a forming crew, total hours calculated based on takeoff total and form production variable
Concrete Crew In Cubic Yards Per Hour – Choose a concrete placement crew, total hours calculated based on total concrete and place production variable
Anchor Bolts – Items calculated based on takeoff total and bolts per column variable
Rebar Crew In Pounds Per Hour – Choose a rebar crew, total hours calculated based on all rebar variables and takeoff total
Rebar For Concrete Wall - Linear
Summary: This assembly is designed for a Linear takeoff.
Variables:
Wall height In - enter the height of the concrete, used to calculate vertical and horizontal rebar
Rebar Waste 1 To 100 - enter a percentage waste factor for rebar
Vertical Rebar Spacing In - enter rebar spacing in inches
Horizontal Rebar Spacing In - enter rebar spacing in inches
Rebar Mat Count - how many mats of rebar are to be installed in the wall
Rebar Stock Length Feet - the length of the rebar you typically order
Bar Lap Count - Click here for a description
Vert Bar Size - the number of the rebar you chose
Horz Bar Size - the number of the rebar you chose
Crew Production Lbs Per Hr - the productivity of the labor crew you chose
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire - based on the number(s) of your rebar chosen in variables and the wall dimensions
Item Groups:
These groups contain a selection of items that must be chosen if required
Vertical Rebar Reinforcing - choose rebar by the foot or pound, length of each will be the wall height, the total considers linear takeoff and rebar spacing variable
Horizontal Rebar Reinforcing - choose rebar by the foot or pound, length will be figured using the wall height, linear takeoff, spacing variable and bar lap count
Rebar Crew In Pounds Per Hour - choose a labor crew whose productivity is specified in the associated variable
Rebar For Continuous Footer - Linear
Summary: This assembly is designed for a Linear takeoff and may work with any concrete takeoff whose primary dimension is length, e.g. beams, stem walls, footings, thickened edges.
Variables:
Footer Width In - width of the concrete, used to figure horizontal/transverse rebar
Continuous Rebar Count - how many runs of rebar go along the length of the concrete
Horizontal Rebar Spacing In - used to calculate horizontal/transverse rebar
Vertical Dowel Spacing In - used to calculate vertical dowels
Vertical Dowel Length Ft - total length of each vertical dowel, including hooks, bends, etc.
Rebar Waste 1 To 100 - enter a percentage waste factor
Rebar Stock Length Feet - the length of the rebar you typically order
Bar Lap Count - Click here for a description
Cont Bar Size - the number of the rebar you chose
Cross Bar Size - the number of the rebar you chose
Vert Dowel Size - the number of the rebar you chose
Crew Production Lbs Per Hr - the productivity of the labor crew you chose
Stirrup Spacing In Feet - used to calculate stirrup rebar
Stirrup Length In Feet - total length of each stirrup
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire - based on the number(s) of your rebar chosen in variables and the footing dimensions
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Continuous Rebar Reinforcing - choose rebar by the pound or linear foot, calculated using count variable, takeoff measurement and bar lap count
Choose Rebar Cross-Bridging - choose rebar by the foot or pound, calculated using takeoff length and horizontal/transverse/cross variables
Add Rebar Chairs - calculated at one chair per continuous rebar run and every 4 feet
Add Vertical Dowels (if used) - choose rebar by the foot or pound, calculated using takeoff length and vertical dowel variables
Rebar Crew In Pounds Per Hour - choose a labor crew whose productivity is specified in the associated variable
Rebar For Stirrups (if used) - Choose rebar by the foot or pound, calculated using takeoff length and stirrup variables
Rebar For Pier Footer - Count
Summary: This assembly is designed for a count takeoff. It is to be used for footings that have rebar in a "grid" layout with options for a top and/or bottom layer.
Variables:
Footer Width Ft - One horizontal dimension of the footing
Footer Height Ft - the other horizontal dimension of the footing
Rebar Count - how many pieces of rebar go one way, this assumes both ways have the same count, so if they are different, an average count should suffice
Top Bar Size - the number of the rebar chosen
Bot Bar Size - the number of the rebar chosen
Crew Production Lbs Per Hr - the productivity of the labor crew chosen
Required Items:
16 Gauge Tie Wire - based on the number(s) of your rebar chosen in variables and the footing dimensions
Item Groups:
These groups contain a selection of items that must be chosen if required
Rebar Each Way @ Bottom - Choose rebar by the foot or by the pound, calculated using the footing dimensions and rebar count
Rebar Each Way @ Top - Choose rebar by the foot or by the pound, calculated using the footing dimensions and rebar count
Rebar Crew In Pounds Per Hr - choose a labor crew whose productivity is specified in the associated variable
Rebar For Slab - Area
Summary: This is based on an Area-type takeoff and may be used for any concrete flatwork.
Variables:
Rebar Waste 1 To 100 - Enter a percentage waste factor
Rebar Stock Length Feet - the length of rebar you typically order
Bar Lap Count - Click here for a description
Rebar Spacing In - the "on-center" number, spacing of the rebar in inches
Bar Size - the number of the rebar you chose
Crew Production Lbs Per Hr - productivity of the crew chosen
Reinforcing Chairs Sq Ft Per Each - square foot spacing of rebar chairs
Required Items:
16 Gauge Tie Wire - based on the number of your rebar chosen in variables and the takeoff dimensions
Item Groups:
These groups contain a selection of items that must be chosen if required
Rebar Reinforcing (On Center Each Way) - choose rebar in feet or pounds
Reinforcing Crew - choose a crew with productivity rate in the related variable
Choose Rebar Chairs - chairs will be calculated based on total takeoff area and spacing variable
Rebar For Spread Footer - Area
Summary: This assembly is designed for an Area-type takeoff and will work for rebar in a "grid" pattern with one or two mats
Variables:
Rebar Waste 1 To 100 - enter a percentage waste factor
Sqft Per Rebar Chair - square foot spacing of rebar chairs
Top Rebar Spacing In - the on-center number for the top mat of rebar
Bottom Rebar Spacing In - the on-center number for the bottom mat of rebar
Rebar Stock Length Feet - the length of rebar you typically order
Bar Lap Count - Click here for a description
Bot Bar Size - the number of rebar chosen
Top Bar Size - the number of rebar chosen
Crew Production Lbs Per Hr - productivity of the crew chosen
Required Items:
16 Gauge Tie Wire - based on the number(s) of your rebar chosen in variables and the takeoff dimensions
Item Groups:
These groups contain a selection of items that must be chosen if required
Bottom Rebar Reinforcing (On Center Each Way) - choose rebar by the foot or pound, calculated using the takeoff total, spacing variable, bar lap count and stock length
Top Rebar Reinforcing (On Center Each Way) - choose rebar by the foot or pound, calculated using the takeoff total, spacing variable, bar lap count and stock length
Add Rebar Chairs (sf per each chair) - calculated using takeoff measurement and spacing variable
Rebar Crew Production - choose a labor crew, calculated by takeoff value and productivity variable
03 31 00 - Foundation
Concrete Column/Pier Footer - Count
Summary: This assembly is designed for a Count takeoff and works for rectangular concrete structures. Rebar will be one or two mats in a grid pattern.
Variables:
Footer Width Ft - One of the horizontal dimensions of the column/pier
Footer Height Ft - The other horizontal dimension
Footer Depth In - the vertical dimension of the column/pier
Concrete Waste 1 To 100 - enter a percentage waste factor for the concrete
Rebar Count - how many pieces of rebar go "one way"
Anchor Bolts Per Column - necessary if using anchor bolts
Excavate Production Cy Per Hr - productivity rate of the excavation crew you choose
Place Production Cy Per Hr - productivity rate of the concrete crew you choose
Depth To Top Of Footer In - if excavating and the top of your footing is below ground level, this is the distance from the top of the footing to ground level, used to calculate total dirt excavated
Top Bar Size - the number (size) of rebar on the top mat
Bot Bar Size - the number (size) of rebar on the bottom mat
Crew Production Lbs Per Hr - productivity rate of the rebar crew you choose
Required Items:
Foundation, Square Feet - total square footage viewed from the top
Footer Count - takeoff count total
Excavation Quantity - total amount excavated equaling the volume of concrete plus volume above determined by "Depth To Top Of Footer In" variable
16 Gauge Tie Wire - determined by rebar calculations and bar size variables
Item Groups:
These groups contain a selection of items that must be chosen if required
Concrete - calculated using the takeoff total and dimension variables
Rebar @ Bottom - the bottom mat of rebar calculated using rebar count and horizontal concrete dimension variables
Rebar @ Top - the top mat of rebar calculated using rebar count and horizontal concrete dimension variables
Anchor Bolts - based on takeoff total and anchor bolt variable
Excavation Crew In Cubic Yards Per Hour - calculated using excavation volume and productivity variable
Concrete Placing Crew - calculated using concrete volume and productivity variable
Rebar Crew In Pounds Of Steel Per Hour - calculated using rebar total and productivity variable
Concrete Column, Round – Count
Summary: This assembly is designed for round columns requiring sonotube forms with vertical and cage rebar. You could also use this for round piers that require the same rebar configuration, not selecting a form item. It is designed for a count takeoff.
Variables:
Column Diameter In – Enter the diameter of the column in inches.
Column Height In – Enter the height (vertical dimension) of the column in inches, can also be the depth if this is a pier.
Concrete Waste 1 to 100 – Enter a percentage waste factor for concrete.
Vertical Rebar Count – Enter the number of pieces of rebar that run vertically in the column.
Rebar Waste 1 to 100 – Enter a percentage waste factor for rebar.
Cage Rebar Spacing In – Enter the spacing of cages in inches.
Form Production Column Per Hr – For your forming labor crew, enter the number of columns your forming crew can install in one hour.
Place Production Cy Per Hr – For your concrete placement crew, enter the amount of concrete they can place in cubic yards in one hour.
Anchors Per Column – The number of anchor bolts required per column.
Vert Bar Size – Used to calculate tie wire and rebar labor crew, enter the vertical rebar’s number (3, 4, 5, etc.).
Cage Bar Size - Used to calculate tie wire and rebar labor crew, enter the cage rebar’s number (3, 4, 5, etc.).
Crew Production Lbs Per Hr – For your rebar placement crew, enter the amount of rebar they can place in pounds.
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire – based on the number(s) of your rebar chosen in variables and the column dimensions.
Poured Columns, Round – a Summary type item that simply reflects the takeoff total.
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete – Items for structural concrete from 2500 to 5500 PSI, calculated based on takeoff total and column dimension variables
Form Material – Contains sonotube items from 8” to 48” diameter
Vertical Rebar – Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the rebar count
Cage Rebar - Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the cage spacing
Formwork Crew In Columns Per Hour – Choose a forming crew, total hours calculated based on takeoff total and form production variable
Concrete Crew In Cubic Yards Per Hour – Choose a concrete placement crew, total hours calculated based on total concrete and place production variable
Anchor Bolts – Items calculated based on takeoff total and bolts per column variable
Rebar Crew In Pounds Per Hour – Choose a rebar crew, total hours calculated based on all rebar variables and takeoff total
Concrete Column, Square – Count (2021)
Summary: This assembly is designed for rectangular concrete columns with vertical and cage rebar and plywood forms.
Variables:
Column Height In – the column’s vertical dimension, whether height or depth, entered in inches
Concrete Waste 1 To 100 – enter a percentage waste factor for concrete
Vertical Rebar Count – how many pieces of rebar are placed vertically in the column
Rebar Waste 1 To 100 – enter a percentage waste factor for rebar
Cage Rebar Spacing In – enter the spacing of your cages as they go up the column in inches
Column Width In – one of the horizontal dimensions of the column
Column Length In – the other horizontal dimension of the column
Form Production SF Per Hour – how many square feet of forming can your forming crew place in an hour
Place Production CY Per Hour – how many cubic yards of concrete your placing crew can do in an hour
Anchors Per Column - how many anchor bolts you need per column
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire – based on the number(s) of your rebar chosen in variables and the column dimensions
Poured Columns, Round – a Summary type item that reflects the takeoff total
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete – Items for structural concrete from 2500 to 5500 PSI, calculated based on takeoff total and column dimension variables
Form Material – Contains sonotube items from 8” to 48” diameter
Vertical Rebar – Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the rebar count
Cage Rebar - Contains rebar items from #3 to #8 in either pounds or feet, calculated based on column dimensions and the cage spacing
Formwork Crew In Columns Per Hour – Choose a forming crew, total hours calculated based on takeoff total and form production variable
Concrete Crew In Cubic Yards Per Hour – Choose a concrete placement crew, total hours calculated based on total concrete and place production variable
Anchor Bolts – Items calculated based on takeoff total and bolts per column variable
Rebar Crew In Pounds Per Hour – Choose a rebar crew, total hours calculated based on all rebar variables and takeoff total
Concrete Grade Beam - 3D
Summary: This assembly requires a Volume 3D takeoff. It is designed for concrete structures with length as the primary dimension with continuous rebar and stirrups.
Variables:
Concrete Waste 1 To 100 - enter a percentage waste factor
Stirrup Spacing In - used to calculate stirrup rebar
Beam Width In - the other horizontal dimension of the footing, used to calculate excavation totals and stirrup rebar
Beam Depth In - the vertical dimension of the beam, used to calculate excavation totals and stirrup rebar
Continuous Rebar Count - how many runs of rebar go along the length of the beam
Formed Side Count - how many sides of the beam need forms
Form Production Lf Per Hr - productivity rate for the forming crew chosen
Place Production Cy Per Hr - productivity rate for the concrete crew chosen
Rebar Waste 1 To 100 - enter a percentage waste factor
Excavation Width In - width of trench to be excavated
Excavation Depth In - depth of trench to be excavated
Excavate Production Cy Per Hr - productivity rate for the excavation crew chosen
Rebar Stock Length Feet - the length of rebar you typically order
Bar Lap Count - Click here for a description
Cont Bar Size - the number of the rebar chosen
Stirrup Bar Size - the number of the rebar chosen
Crew Production Lbs Per Hr - productivity rate for the rebar crew chosen
Required Items:
These items will be added without having to choose them
Grade Beam Linear Feet - summary item reflecting the linear component of your takeoff
16 Gauge Tie Wire - calculated using the rebar totals and size variables
Excavation Quantity - total amount to be excavated
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - based on takeoff volume
Continuous Rebar - by the foot or pound, based on linear footage from the takeoff, bar lap count and continuous count variable
Rebar Stirrups - choose rebar by the foot or pound, calculated using beam dimensions and spacing variable
Add Form Panels - based on beam dimensions and count variable
Choose Excavation Crew - requires the productivity variable to calculate
Choose Forming Crew - requires the productivity variable to calculate
Choose Concrete Placing Crew - requires the productivity variable to calculate
Rebar Crew In Pounds Of Steel - requires the productivity variable to calculate
Concrete Spread Footer - 2D
Summary: This assembly requires a Volume 2D takeoff and offers 1 or 2 mats of rebar.
Variables:
Concrete Waste 1 To 100 - enter a percentage waste factor
Rebar Waste 1 To 100 - enter a percentage waste factor
Sqft Per Rebar Chair - the square foot spacing of rebar chairs
Top Rebar Spacing In - your on center number in inches
Bottom Rebar Spacing In - your on center number in inches
Depth To Top Of Footer Inches - if excavating and the top of your footing is below ground level, this is the distance from the top of the footing to ground level, used to calculate total dirt excavated
Excavate Production Cy Per Hr - the productivity rate of the crew chosen
Place Production Cy Per Hr - the productivity rate of the crew chosen
Anchor Bolt Count - number of bolts per footer
Rebar Mat Count - this variable is not currently used
Rebar Stock Length Feet - the length of rebar you typically order
Bar Lap Count - Click here for a description
Bot Bar Size - the number of the rebar you chose
Top Bar Size - the number of the rebar you chose
Crew Production Lbs Per Hr - the productivity rate of the crew chosen
Required Items:
These items will be added without having to choose them
Foundation, Square Feet - summary item showing the area of the footing from the top
16 Gauge Tie Wire - calculated using the rebar totals and size variables
Excavation Quantity - calculated using the concrete total, takeoff area and depth to top of footing variable
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - based on takeoff total volume
Bottom Rebar Reinforcing (On Center Each Way) - choice of rebar by the foot or pound, giving you one of the mats of rebar in the footing
Top Rebar Reinforcing (On Center Each Way) - choice of rebar by the foot or the pound, giving you one of the mats of rebar in the footing
Add Rebar Chairs (sf per each chair) - calculated using the area component from your takeoff and the spacing variable
Excavation Crew (depth to footer & cy per hour) - requires the productivity variable to calculate
Crew To Place Concrete - requires the productivity variable to calculate
Choose Anchor Bolts - total count of footers times the anchor bolt variable
Rebar Crew In Pounds Of Steel Per Hour - requires the productivity variable to calculate
Concrete Wall - 3D
Summary: This assembly requires a Volume 3D takeoff and yields vertical and horizontal rebar
Variables:
Wall Height In - the height of the concrete wall, used to calculate rebar
Concrete Waste 1 To 100 - enter a percentage waste factor
Rebar Waste 1 To 100 - enter a percentage waste factor
Waler Runs - used for calculating waler brackets and snap ties
Vertical Rebar Spacing In - on center spacing for vertical rebar along the length of the wall
Horizontal Snap Tie Spacing In - on center spacing of snap ties along the length of the wall
Horizontal Rebar Spacing In - on center spacing of horizontal rebar going up the wall
Form Production Sf Per Hr - the productivity rate of the crew chosen
Place Production Cy Per Hr - the productivity rate of the crew chosen
Linear Ft Per Anchor Bolt - anchor bolt spacing
Rebar Mat Count - how many mats or "grids" of rebar present in the wall
Rebar Stock Length Feet - the length of rebar you typically order
Bar Lap Count - Click here for a description
Vert Bar Size - the number of the rebar you chose
Horz Bar Size - the number of the rebar you chose
Crew Production Lbs Per Hr - the productivity rate of the crew chosen
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire - calculated using the rebar totals and size variables
Poured Wall, Linear Feet - summary item reflecting the linear component of the takeoff
Poured Wall, Square Feet - summary item reflecting the square footage of the wall
A16 Omni Wedge - based on the linear footage of the takeoff, waler run variable and snap tie spacing
Item Groups:
These groups contain a selection of items that must be chosen if required
Concrete (Optional) - calculated using the takeoff total
Rebar Vertical Reinforcing - available by the foot or pound, calculated using wall dimensions, spacing variable and mat count
Rebar Horizontal Reinforcing - available by the foot or pound, calculated using wall dimensions, spacing variable and bar lap count
Form Panels (Optional) - calculated using wall dimensions
Add For Waler Brackets - calculated using the length of the wall and waler bracket variable
Snap Ties (optional) - calculated using the length of the wall, snap tie spacing and waler bracket variables
Form Crew - requires the productivity variable to calculate
Concrete Placing Crew - requires the productivity variable to calculate
Anchor Bolts (optional) - calculated using the length of the wall and anchor bolt spacing variable
Waterstop (Optional) - equals the length of the wall
Rebar Crew In Pounds of Steel - requires the productivity variable to calculate
Continuous Footer - Linear
Summary: This assembly is designed for a Linear takeoff and offers continuous, transverse, vertical and stirrup rebar
Variables:
Footer Width In - used to calculate concrete volume and transverse rebar
Concrete Waste 1 To 100 - enter a percentage waste factor
Continuous Rebar Count - the number of rebar runs going along the length of the footing
Horizontal Rebar Spacing In - used to calculate horizontal/transverse rebar
Vertical Dowel Spacing In - used to calculate vertical dowels
Vertical Dowel Length Ft - the total length of one vertical dowel, including any bends, J's or hooks
Excavate Production Lf Per Hr - the productivity rate of the crew you chose
Place Production Cy Per Hr - the productivity rate of the crew you chose
Rebar Waste 1 To 100 - enter a percentage waste factor
Depth To Top Of Footer In - if excavating and the top of your footing is below ground level, this is the distance from the top of the footing to ground level, used to calculate total dirt excavated
Rebar Stock Length Feet - the length of rebar you typically order
Bar Lap Count - Click here for a description
Footer Depth In - the vertical dimension of the footing
Cont Bar Size - the number of rebar you chose
Cross Bar Size - the number of rebar you chose
Vert Dowel Size - the number of rebar you chose
Crew Production Lbs Per Hr - the productivity rate of the crew you chose
Stirrup Spacing In Feet - used for calculating stirrup rebar
Stirrup Length In Feet - total length of one stirrup piece
Required Items:
These items will be added without having to choose them
Foundation, Linear Feet - summary item reflecting the linear takeoff total
16 Gauge Tie Wire - calculated using the rebar totals and size variables
Foundation, Square Feet - summary item reflecting the area of the footing when viewed from above
Excavation Quantity - total amount of dirt excavated calculated using footing volume and depth to top of footer variable
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - calculated using the takeoff total and dimension variables
Rebar Continuous Reinforcing - by the foot or pound, calculated using linear takeoff total, rebar count variable and bar lap count
Rebar Cross-Bridging (IF USED) - transverse rebar by the foot or pound, calculated using linear takeoff total, rebar spacing variable and footing width variable
Add Rebar Chairs - one chair per continuous rebar count spaced at 4 feet
Add Rebar Vertical Dowels - by the foot or pound, calculated using linear takeoff total, length and spacing variables
Excavation Crew By linear Feet Of Trench - requires the productivity variable to calculate
Rebar Crew By Pounds Of Steel - requires the productivity variable to calculate
Concrete Placing Crew - requires the productivity variable to calculate
Rebar Stirrups (IF USED) - by the foot or pound, calculated using the linear takeoff total, length and spacing variables
Continuous Footer, Earth Formed - 3D
Summary: This assembly is requires a Volume 3D takeoff and offers continuous, transverse, vertical and stirrup rebar
Variables:
Footer Width In - used to calculate horizontal/transverse rebar
Concrete Waste 1 To 100 - enter a percentage waste factor
Continuous Rebar Count - the number of rebar runs going along the length of the footing
Horizontal Rebar Spacing In - used to calculate horizontal/transverse rebar
Vertical Dowel Length Ft - used to calculate vertical rebar
Excavate Production Lf Per Hr - the productivity rate of the crew you chose
Reinforcing Production Lf Per Hr - the productivity rate of the crew you chose
Place Production Cy Per Hr - the productivity rate of the crew you chose
Rebar Waste 1 To 100 - enter a percentage waste factor
Depth To Top Of Footer In - if excavating and the top of your footing is below ground level, this is the distance from the top of the footing to ground level, used to calculate total dirt excavated
Rebar Stock Length Feet - the length of rebar you typically order
Bar Lap Count - Click here for a description
Cont Bar Size - the number of rebar you chose
Cross Bar Size - the number of rebar you chose
Vert Dowel Size - the number of rebar you chose
Vertical Dowel Spacing In - used to calculate vertical dowels
Crew Production Lbs Per Hr - the productivity rate of the crew you chose
Excavation Production Cy Per Hour - the productivity rate of the crew you chose
Stirrup Spacing In Feet - used to calculate stirrups
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire - calculated using the rebar totals and size variables
Foundation, Linear Feet - summary item reflecting the linear takeoff total
Foundation, Square Feet - summary item reflecting the area of the footing when viewed from above
Excavation Quantity - total amount of dirt excavated calculated using footing volume and depth to top of footer variable
Item Groups:
These groups contain a selection of items that must be chosen if required
Select Concrete - calculated using the takeoff volume total
Add Continuous Reinforcing - by the foot or pound, calculated using linear takeoff total, rebar count variable and bar lap count
Add Rebar Cross-Bridging (IF USED) - transverse rebar by the foot or pound, calculated using linear takeoff total, rebar spacing variable and footing width variable
Add Rebar Chairs - one chair per continuous rebar count spaced at 4 feet
Add Rebar Vertical Dowels - by the foot or pound, calculated using linear takeoff total, length and spacing variables
Excavation Crew Per linear Feet Of Trench - requires the productivity variable to calculate
Reinforcing Crew Per linear Feet Of Trench - requires the productivity variable to calculate
Concrete Placing Crew - requires the productivity variable to calculate
Reinforcing Crew per Pound - requires the productivity variable to calculate
Excavation Crew Per CY - requires the productivity variable to calculate
Rebar Stirrups (IF USED) - by the foot or pound, calculated using the linear takeoff total, length and spacing variables
03 33 13 – Slab On Grade
Concrete Building Slab On Grade - 2D
Summary: This assembly requires a Volume 2D takeoff and yields concrete, aggregate base, and WWM reinforcing. Rebar must be added using a separate assembly.
Variables:
Base Depth In - used to calculate aggregate base
Concrete Waste 1 To 100 - enter a percentage waste factor
Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
Finish Grade Production Sf Per Hr - the productivity rate of the crew you chose
Reinforcing Chairs Sq Ft Per Ea - the square foot spacing of rebar chairs
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - calculated using the takeoff volume
Choose If Using WWM Reinforcing - calculated based on the square footage from the takeoff
Add Aggregate Base If Required - calculated using square footage from the takeoff and the base depth variable
Add Vapor Barrier If Required - calculated using the square footage from the takeoff
Add For Fibrous Reinforcing - based on the volume from the takeoff
Choose Finish - summary or labor items reflecting the square footage of the takeoff
Choose Crew For Place & Finish - requires the productivity variable to calculate
Choose Crew For Finish Grade Work - requires the productivity variable to calculate
Rebar Chairs - calculated using the area from the takeoff and spacing variable
Concrete Paving On Grade - 2D
Summary: This assembly requires a Volume 2D takeoff and yields concrete, aggregate base, and WWM reinforcing. Rebar must be added using a separate assembly.
Variables:
Base Depth In - used to calculate aggregate base
Concrete Waste 1 To 100 - enter a percentage waste factor
Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
Finish Grade Production Sf Per Hr - the productivity rate of the crew you chose
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - calculated using the takeoff volume
Choose If Using WWM Reinforcing - calculated based on the square footage from the takeoff
Add Aggregate Base If Required - calculated using square footage from the takeoff and the base depth variable
Add Vapor Barrier If Required - calculated using the square footage from the takeoff
Add For Fibrous Reinforcing - based on the volume from the takeoff
Choose Finish - summary or labor items reflecting the square footage of the takeoff
Choose Crew For Place & Finish - requires the productivity variable to calculate
Choose Crew For Finish Grade Work - requires the productivity variable to calculate
Concrete Sidewalk On Grade - 2D
Summary: This assembly requires a Volume 2D takeoff and yields concrete, aggregate base, and WWM reinforcing. Rebar must be added using a separate assembly.
Variables:
Base Depth In - used to calculate aggregate base
Concrete Waste 1 To 100 - enter a percentage waste factor
Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
Finish Grade Production Sf Per Hr - the productivity rate of the crew you chose
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - calculated using the takeoff volume
Choose If Using WWM Reinforcing - calculated based on the square footage from the takeoff
Add Aggregate Base If Required - calculated using square footage from the takeoff and the base depth variable
Add Vapor Barrier If Required - calculated using the square footage from the takeoff
Add For Fibrous Reinforcing - based on the volume from the takeoff
Choose Finish - summary or labor items reflecting the square footage of the takeoff
Choose Crew For Place & Finish - requires the productivity variable to calculate
Choose Crew For Finish Grade Work - requires the productivity variable to calculate
03 33 19 – Elevated Concrete
Concrete Stair Pans - 2D
Summary: This assembly requires a Volume 2D takeoff and only concrete, labor and a square foot summary.
Variables:
Concrete Waste 1 To 100 - enter a percentage waste factor
Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - calculated using the takeoff volume
Choose Finish - summary or labor items reflecting the square footage of the takeoff
Choose Crew For Place & Finish - requires the productivity variable to calculate
Elevated Concrete Beam - 3D
Summary: This assembly requires a Volume 3D takeoff and offers continuous and stirrup rebar.
Variables:
Concrete Waste 1 To 100 - enter a percentage waste factor
Stirrup Spacing In - used to calculate stirrups
Beam Width In - the horizontal dimension (along with the length from the takeoff) of the beam, used to calculate stirrups
Beam Depth In - the vertical dimension of the beam, used to calculate stirrups
Continuous Rebar Count - how many runs of rebar go along the length of the beam
Formed Side Count - how many side of the beam need forms
Form Production Lf Per Hr - the productivity rate of the crew you chose
Place Production Cy Per Hr - the productivity rate of the crew you chose
Rebar Waste 1 To 100 - enter a percentage waste factor
Rebar Stock Length Feet - the length of rebar you typically order
Bar Lap Count - Click here for a description
Stirrup Bar Size - the number of rebar you chose
Crew Production Lbs Per Hr - the productivity rate of the crew you chose
Cont Bar Size - the number of rebar you chose
Required Items:
These items will be added without having to choose them
16 Gauge Tie Wire - calculated based on the takeoff volume
Elevated Concrete Beam - Summary item reflecting the linear component of your takeoff
Shoring Jack - one every 4 feet of takeoff length
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - calculated using the takeoff volume
Continuous Rebar - by the foot or pound, calculated using linear takeoff total, rebar count variable and bar lap count
Rebar Stirrups - by the foot or pound, calculated using beam dimensions and spacing variables
Add Form Panels - calculated using the linear footage from the takeoff and side count variable
Form Crew In Linear Feet per Hour - requires the productivity variable to calculate
Rebar Crew In Pounds Per Hour - requires the productivity variable to calculate
Concrete Placing Crew In Cubic Yards Per Hour - requires the productivity variable to calculate
Elevated Concrete Slab - 2D
Summary: This assembly requires a Volume 2D takeoff. Rebar is not included, so use a separate assembly if needed.
Variables:
Concrete Waste 1 To 100 - enter a percentage waste factor
Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - calculated using the takeoff volume
Choose If Using WWM Reinforcing - based on the area component of the takeoff
Add For Fibrous Reinforcing - based on the volume of the takeoff
Choose Finish - summary or labor items reflecting the square footage of the takeoff
Choose Crew For Place & Finish - requires the productivity variable to calculate
03 47 00 – Site Cast Concrete
Lift-Slab Concrete - 2D
Summary: This assembly requires a Volume 2D takeoff
Variables:
Concrete Waste 1 To 100 - enter a percentage waste factor
Form Production Sf Per Hr - the productivity rate of the crew you chose
Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
Erection Production Sf Hr - the productivity rate of the crew you chose
Required Items:
These items will be added without having to choose them
Form Release, Wood Forms - calculated using the area from the takeoff
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - based on the volume from the takeoff
Choose Form Crew - requires the productivity variable to calculate
Choose Place & Finish Crew - requires the productivity variable to calculate
Choose Erection Crew - requires the productivity variable to calculate
Tilt-Up Concrete - 2D
Summary: This assembly requires a Volume 2D takeoff
Variables:
Concrete Waste 1 To 100 - enter a percentage waste factor
Form Production Sf Per Hr - the productivity rate of the crew you chose
Place Finish Production Sf Per Hr - the productivity rate of the crew you chose
Erection Production Sf Hr - the productivity rate of the crew you chose
Required Items:
These items will be added without having to choose them
Form Release, Wood Forms - calculated using the area from the takeoff
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - based on the volume from the takeoff
Choose Form Liner - equal to the area from the takeoff
Choose Form Crew - requires the productivity variable to calculate
Choose Place & Finish Crew - requires the productivity variable to calculate
Choose Erection Crew - requires the productivity variable to calculate
32 16 00 – Curbs & Gutters
Curb With Gutter, "L" Shaped - Linear
Summary: This assembly is designed for a Linear takeoff. There is no rebar included.
Variables:
Gutter Width In - horizontal dimension used to calculate the gutter portion of concrete
Curb Height In - vertical dimension used to calculate the curb portion of concrete
Gutter Depth In - vertical dimension used to calculate the gutter portion of concrete
Concrete Waste Percentage - enter a percentage waste factor
Base Stone Width In - horizontal dimension used to calculate aggregate base
Base Stone Depth In - vertical dimension used to calculate aggregate base
Form Production Lf Per Hr - the productivity rate of the crew you chose
Place Finish Production Lf Per Hr - the productivity rate of the crew you chose
Grading Production Lf Per Hr - the productivity rate of the crew you chose
Curb Width In - horizontal dimension used to calculate the curb portion of concrete
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - based on the linear footage from the takeoff and curb dimension variables
Choose Curb Type - offers summary items describing the curb and reflecting the linear footage from the takeoff
Add Aggregate Base Stone - calculated using Linear takeoff total and stone dimension variables
Choose Grading Crew - requires the productivity variable to calculate
Choose Form Crew - requires the productivity variable to calculate
Choose Place & Finish Crew - requires the productivity variable to calculate
Flush Curb - Linear
Summary: This assembly is designed for a linear takeoff
Variables:
Curb Width In - one horizontal dimension of the concrete
Curb Height In - the vertical dimension of the concrete
Concrete Waste 1 To 100 - enter a percentage waste factor
Stone Base Depth In - used to calculate aggregate base
Grade Production Lf Per Hr - the productivity rate of the crew you chose
Form Production Lf Per Hr - the productivity rate of the crew you chose
Place Finish Production Lf Per Hr - the productivity rate of the crew you chose
Required Items:
These items will be added without having to choose them
DOT Flush Curb & Gutter - a summary item reflecting the linear footage from the takeoff
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - based on the linear footage from the takeoff and curb dimension variables
Add Aggregate Base Stone - calculated using Linear takeoff total and stone depth variable
Choose Grading Crew - requires the productivity variable to calculate
Choose Form Crew - requires the productivity variable to calculate
Choose Place & Finish Crew - requires the productivity variable to calculate
Vertical Curb, Box Shaped - Linear
Summary:
Variables:
Curb Width In - one horizontal dimension of the concrete
Curb Height In - the vertical dimension of the concrete
Concrete Waste 1 To 100 - enter a percentage waste factor
Stone Base Depth In - used to calculate aggregate base
Grade Production Lf Per Hr - the productivity rate of the crew you chose
Form Production Lf Per Hr - the productivity rate of the crew you chose
Place Finish Production Lf Per Hr - the productivity rate of the crew you chose
Required Items:
These items will be added without having to choose them
Box Curb - a summary item reflecting the linear footage from the takeoff
Item Groups:
These groups contain a selection of items that must be chosen if required
Choose Concrete - based on the linear footage from the takeoff and curb dimension variables
Add Aggregate Base Stone - calculated using Linear takeoff total and stone depth variable
Choose Grading Crew - requires the productivity variable to calculate
Choose Form Crew - requires the productivity variable to calculate
Choose Place & Finish Crew - requires the productivity variable to calculate
Concrete Formwork – 2D
Summary: This assembly will work with any linear or area-based takeoff, but is best suited for areas.
Variables:
Stake Spacing In Feet - required to calculate the stakes items
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Group 2 Forms - calculated by dividing the linear perimeter of the takeoff by the length of the chosen board
Group 1 Forms - calculated by dividing the linear perimeter of the takeoff by the length of the chosen board
Stakes - calculated using the linear perimeter of the takeoff and stake spacing variable
Concrete Formwork - Linear
Summary: This assembly will work with any linear or area-based takeoff, but is best suited for linear-type takeoffs like continuous footings and beams.
Variables:
Stake Spacing In Feet - required to calculate the stakes items
Required Items:
There are no required items in this assembly
Item Groups:
These groups contain a selection of items that must be chosen if required
Group 2 Forms - calculated by dividing the linear perimeter of the takeoff by the length of the chosen board and multiplying by 2
Group 1 Forms - calculated by dividing the linear perimeter of the takeoff by the length of the chosen board and multiplying by 2
Stakes - calculated using the linear perimeter of the takeoff and stake spacing variable